Re: Great but expensive and unpredictable solution
AZskibum   7/30/2014 12:06:10 PM
NO RATINGS
Zavi, I totally agree. Tapeout is a huge process, so extreme caution should be exercised in any decision to short-change part of the verification for an "early tapeout." Although there is obviously time-to-market value in putting silicon in the customer's hands as early as possible, even with an expectation of a second pass, the silicon must be extremely functional or else the customer can't do much with it.

So how do you decide which parts of the verification plan can be bypassed for an early tapeout? A good conservative approach is to assume that anything that has not been verified is not going to work. Which parts of the chip can you and the customer afford to not have working on the first pass?

Another criteria for early tapeout I have seen, which is also risky and unpredictable, is the idea that "as long as it's functional, we can deal with out of spec parametrics on the next pass." The problem there is that you don't just design for functionality in some abstract sense -- you design to meet certain functionality and parametric performance over a space of PVT corners. Suppose for example, our design includes a voltage regulator, but due to short-cutting the verification, we didn't prove that we meet the max load current spec over all corners, with parasitics, and when our silicon comes back, we find that the customer will not be able to run his application as intended, due to the regulator failing to meet its load current spec. Is that "just a parametric" issue, or is the IC not fully functional in the customer's system?

Whichever way that question is answered, the bigger issues are cost, lost time, possibly lost market window or lost design wins if customers have other options besides waiting for you to do a second pass. The difference between an early tapeout and a thoroughly verified tapeout can be the difference between a profitable product launch and a big money sink.

MikeBartley
User Rank
Freelancer
Re: Risks and Rewards of early tapeout
MikeBartley   7/30/2014 8:34:04 AM
NO RATINGS
This is indeed a good idea - it allows fast fixing of bugs in silicon with minimal cost (at the cost of extra die). This could also be helpful to fix DOA bugs when using the silicon as a verificatio platform

BillM210
User Rank
Rookie
Risks and Rewards of early tapeout
BillM210   7/29/2014 10:08:44 AM
NO RATINGS
Back in the late 1980's/early 1990's while at VLSI Technology, we always put a sample of spare gates into any ASIC design that we taped out.  Some customers had tight schedules to hit their primary selling time (Christmas sales).  To achieve the volume mfg that was required, it was critical to have safeguards just in case something was overlooked during their verification.  VLSI Tech (fab) would hold some wafers prior to metallization just in case some bugs were found.  Using this technique, our customer never missed their market and I would bet that this technique was used over 50% of the time (yes, either they missed all the requirements or the requirements had changed).  By integrating spare gates that had inputs tied to VSS, it allowed very fast changes with minimal mask charges and more importantly extremely fast re-spin of new silicon.  But this approach required careful and diligent hand editing of the physical database to alter metal/contact layers as well as a fab that was willing to split a lot.  To my recollection, if a re-spin was required, it only required one mask change.  Although designs requiring a metal re-spin were not considered a "first pass" success, it was very successful from the customer's perspective.

MikeBartley
User Rank
Freelancer
Re: Good reference
MikeBartley   7/24/2014 4:50:55 AM
NO RATINGS
Thanks Roman

One other economic consideration is customer early engagement. If the early silicon is good enough for the client to use then they can often use it to clarify their requirements, start product development, etc

Mike

MikeBartley
User Rank
Freelancer
Re: Not a substitute for advanced verification methods
MikeBartley   7/24/2014 4:48:52 AM
NO RATINGS
Thanks Roger

Your comparison with FPGA is very appropriate. We are also seeing the FPGA world move towards more simulation and less lab (although adoption of advanced techniques needs some persuasion!)

We encourage our customers to take a Requirements Driven Verification approach which helps to ensure a high level of confidence in the main user requirments and use cases thus reducing the likelihood of DOA

Mike

 

RogerSabbagh
User Rank
Rookie
Not a substitute for advanced verification methods
RogerSabbagh   7/23/2014 6:11:15 PM
NO RATINGS
Mike,

Thanks for this succinct presentation of the trade-offs that should be considered when planning for early tapeout. The key point here is to have a plan for this!

I have been part of design teams that have done this before - sometimes called the two-pass approach. For the first pass, some of the design and/or verification tasks may be incomplete, but the chip is spun early to get system integration started. For any features that have been implemented but not fully tested, you have to assume they will be broken and make sure you can live without them with bypass/disable functions. This enables early system testing to iron out issues at that level and speed up s/w development and integration. All good stuff.

However, as your DAC panelists concluded, this is not a substitute for advanced verification methods! Just ask the guys designing complex FPGAs today. They can't use the "burn-and-learn" approach of the past anymore. H/W debug in the lab is much too resource intesive. A cost/benefit analysis will favor investing in advanced methods such as:
  • constrained random simulation with UVM
  • formal verification with formal apps
  • intelligent testbench automation
  • etc.

Roger

Zavi_#1
User Rank
Rookie
Great but expensive and unpredictable solution
Zavi_#1   7/23/2014 11:18:06 AM
NO RATINGS
Firstly, how we define "early" tapeout? Which stage is early in the whole development cycle? That could be a different answer to different products and different companies.
Secondly, early tapeout could bring absolute benefits for verification. But  it may be confined in a narrow scope for corner bugs not normal bugs which can be caught easily by normal flow. Maybe accelation in mix-signal simulation and early development for bios, driver and software could be potential advantages. Tapeout is a hugh process and involves both frontend and backend efforts. We should take extra work for DE and PD into consideration when evaluating the ecnomical gains and losses.

roman.wang
User Rank
Rookie
Re: Good reference
roman.wang   7/23/2014 10:59:28 AM
NO RATINGS

Good article.

 

Is it possible for verification team to iron out all the bugs before taping out within the tough project schedule?

No one could have confidence to say yes. the re-spin usually happens in most of team.

 

The verification team may take the silicon as the HW accelerator for re-spin. it may be too late for market.

 

So the early tape-out is a smart verificaiton but more $$ cost.

 

This should be a tradeoff between $$ and time-to-market. 

I guess the re-spin may miss the market and take more $$.

 

any thought?

MikeBartley
User Rank
Freelancer
Re: Good reference
MikeBartley   7/23/2014 9:20:17 AM
NO RATINGS
Hi Darren

You're right - econmics should dominate the decision. However, TTM (time to market) is often a key issue in economics (imageine a new mobile phone missing its Christmas launch). So the fab cost might be justified on a TTM calculation

Mike

tommyma518
User Rank
Rookie
Re: Good reference
tommyma518   7/23/2014 6:22:42 AM
NO RATINGS
yes, i think so

Page 1 / 2   >   >>
Most Recent Comments
Hailey McKeefry
 
AKH0
 
sleibson-xilinx
 
David Ashton
 
mhrackin
 
Max The Magnificent
 
mhrackin
 
Max The Magnificent
 
Max The Magnificent
Radio
NEXT UPCOMING BROADCAST
EE Times Senior Technical Editor Martin Rowe will interview EMC engineer Kenneth Wyatt.
Top Comments of the Week
Like Us on Facebook

Datasheets.com Parts Search

185 million searchable parts
(please enter a part number or hit search to begin)
EE Times on Twitter
EE Times Twitter Feed
Flash Poll