Slideshow: GlobalFoundries expanding in Dresden

Peter Clarke

6/18/2012 12:40 PM EDT

A welcome at GlobalFoundries Fab 1
 Our host for the day and the first speaker was Rutger Wijburg, vice president and general manager of Fab 1. A former NXP guy who joined GlobalFoundries with effect from Oct. 1, 2011, Wijburg has been sorting out some of the problems that struck GlobalFoundries 28-nm manufacturing in Dresden during 2011. To the visiting journalists he gave a passionate speech that touched on the importance of retaining manufacturing in Europe.



Rutger Wijburg, vice president and general manager of Fab 1 for GlobalFoundries


Wijburg also spoke about progress made at the wafer fab in the production of 28-nm silicon and the increase of the manufacturing capacity through a $3 billion expansion plan to bring up a 12,000 square foot cleanroom known as the Annex (see Dresden fab could host 20-nm, 450-mm wafers)




Click on image to enlarge.

More details of the Fab 1 complex, formerly Fab 30 and Fab 36 belonging to Advanced Micro Devices Inc.




stippu

6/18/2012 11:14 PM EDT

Great pictures of the inside of a fab, Peter. Looking at this, reminds me back to the plant that Flextronics had set up here ( it was not a fab but am OEM unit and that was one of the firsts we had in the Indian southern city of Chennai. ANd, that took a long time to build too, to the necessary specs. And, when we in India keep talking about setting up a fab, I can just about imagine the time it is going to take and will we ever be able to maintain the quality. Right from clean water to stable electricity, there is a problem in every city ( with 1-2 hr power cuts in every city even today).. and we talk about setting a world class fab. Sure,it is a dream and we like to dream big but... all players, including the government have to really pull it off, in a big way and I mean really big way. Lets wait and see. These pictures set me thinking how we, in India can do it.. and the operative word is when.

Sign in to Reply



rwik78

6/19/2012 8:26 PM EDT

GF has postponed fab plans in Abu Dhabi, where ATIC (their prime investor and stakeholder) is based. My guess is that would take maybe another 5-8 years depending on GF profits and global semiconductor economy.

Doubt any expansion plans in India makes sense. In India: Design, yes, semi manufacturing? There is no ecosystem, no local technicians, and infra is a disaster. So I dont think that makes any sense whatsoever.

Sign in to Reply



peter.clarke

6/19/2012 7:22 AM EDT

The bad news Sufia is that when I asked GlobalFoundries people about whether stories that linked the company to the Indian fab plan process they said they have no idea where these stories come from.

As to the power supply issue, I don't think that is a problem. In Dresden GlobalFoundries runs its own power station to run the plant and puts the excess electricity it produces into the German grid.

I can imagine the same set-up could be created in India.

However, access to enormous volumes of water might be an issue.

Sign in to Reply



iniewski

6/19/2012 9:31 AM EDT

Great pics from inside the fab Rick...pretty rare...although I can't say I learned anything from them ;-)...Kris

Sign in to Reply



wilber_xbox

6/19/2012 10:45 AM EDT

I had heard that GF has put the expansion in Germany on hold following the bad economic conditions in Europe and GF's own financial problems. So, this visit is just a pre-committed journalist's visit or GF is back on track?

Sign in to Reply



SiliconAsia

6/19/2012 1:01 PM EDT

GF is losing a lead customer AMD at 28nm to TSMC and we have not heard that anyone iso back-filling the Dresden fab yet! As foundry sales cycle is long and technology bring-ups are tedious, it will be a while when GF can be back on track if they can....

Sign in to Reply



ZaK325

6/20/2012 7:37 AM EDT

This is completely false. In fact, demand is such that TSMC cannot come close to filling AMDs orders alone (let alone yield well at the node), and they will continue to be a key customer at the GF site. Regardless GF has numerous other extremely promising contracts to fulfill for several years to come, hence the EXPANSION projects in both Germany and New York.

Typical GF slander-trolling post above.

Sign in to Reply



KB3001

6/20/2012 10:41 AM EDT

Nice report, Peter. rwik78's post above reminded me of GF's plans to build a fab in Abu-Dhabi, any news on this?

Sign in to Reply



peter.clarke

6/21/2012 7:32 AM EDT

@KB3001

Regarding Abu Dhabi, noithing substantial.

Rutger Wijburg, general manager at Fab 1, told me that the vision to build a wafer fab in Abu Dhabi is still in place but the timetable has been pushed back.

The original timetable called for ground-breaking in 2012 and chips out in 2014.

I suspect groundbreaking time may become more likely when Fab 8 in Malta, Saratoga County, New York is in volume production.

But the ATIC sovereign wealth fund has been burning money at a tremendous rate. DO they have the appetite for another $5 billion to $10 billion commitment in a location where almost all the workforce would have to be parachuted in.

And it would not be great news for Dresden as it would probably reduce the chances of 20-nm upgrades at that fab complex. We will see.

Sign in to Reply



jeremybirch

6/21/2012 12:41 PM EDT

Apart from loads of oil cash to invest and a liberal supply of sand, not sure why a fab in Abu Dhabi makes any sense at all. There is precious little local skilled labour force, and an awful lot of dust to cope with!

Sign in to Reply



KB3001

6/22/2012 4:12 AM EDT

The skilled force can come from somewhere else jeremybirch, there are more foreigners living in UAE than locals :-) I agree that setting a fab there does not make much sense on technical grounds but ATIC owns GF, so that's a good enough reason :-) I do not see why would they would otherwise pump billions of dollars into a distant business that is not even breaking even.

Sign in to Reply



jeremybirch

6/21/2012 12:44 PM EDT

and if the water has to come from desalination it is going to be rather costly

Sign in to Reply



m00nshine

6/21/2012 11:56 PM EDT

GF is in the position of having to do something extraordinary to avoid becoming a distant 3rd rate player to the likes of TSMC and Samsung in the years to come. Nothing described here fits that bill, whereas TSMC and samsung continue to invest billions every year in new capacity construction and retrofit/upgrade. And they don't seem to take 4 years to get a fab up and running like GF is doing in new york. So how can GF compete and grow their business, and what volume customers (aside from AMD) would want to go to GF with those obvious limitations?

Sign in to Reply



Richy Reef

6/22/2012 12:10 AM EDT

I 2nd that thought.

Sign in to Reply



ZaK325

6/24/2012 8:03 AM EDT

I find it somewhat comical how so many assume that GF doesn't already have volume customers contracted and lined-up for years to come... And also that AMD is the only major company-customer simply because they are the only (obvious) one publicly known. Are we to believe that they are that horribly unprepared?
Do folks truly believe that the *producing* fab in New York is simply idle and waiting for volume customers... when AMD doesn't even have a single product project in that fab? Hmm...

Sign in to Reply



peter.clarke

6/25/2012 12:55 PM EDT

And as Rutger Wijburg said in the second half of 2012 more than 50 percent of the output of Fab 1 in Dresdden, which currently stands at about 50,000 wafer starts per month, will not be for AMD.

So that means more than 25,000 wafers per month heading towards new foundry customers of GlobalFoundries.

Sign in to Reply



Please sign in to post comment

Navigate to related information

Datasheets.com Parts Search

185 million searchable parts
(please enter a part number or hit search to begin)