re: R&D predictability: The path to profitability
RCollett   1/29/2011 12:53:23 AM
NO RATINGS
Robotics Developer, Management thrives on data -- it makes decision-making so much easier, because it takes some of the risk out of the equation. Hard facts and data are therefore a powerful tool for persuading management that a project's schedule is wholly unrealistic. The data must unequivocally show that even if the team acheived best-in-class productivity, the schedule is still not achievable because the staffing allocated to the project is not communsurate with the design's complexity and the schedule constraint. When presented with this, management has little choice but to reduce the scope of the project, relax the schedule constraint, add more resources and/or reblance the project portfolio (i.e. reduce the number of projects). Thanks for the comment. Ron

Robotics Developer
User Rank
Rookie
re: R&D predictability: The path to profitability
Robotics Developer   1/26/2011 4:44:40 AM
NO RATINGS
An interesting article, I have worked in the semi industry for more than 15 years and never found a schedule realistic. Too often the designers presented a real schedule to the management and it was tweaked to meet some arbitrary set of deadlines. This is oftentimes the real cause of "schedule slip" it is non-realistic schedules being adopted as real. Specs do change, resources do disappear, software has issues these are not unexpected and should be accounted for but as I stated the real schedule does not meet the management's target dates. Until that is addressed, development will always be "late".

RCollett
User Rank
Rookie
re: R&D predictability: The path to profitability
RCollett   1/26/2011 2:56:52 AM
NO RATINGS
@new2coding, Well stated -- it is all about company culture. Politics and project planning often go hand-in-hand, because the project planning phase is when funding decisions are made. It is almost axiomatic that money begets politics. In my experience, the most effective and efficient way to cut through politics is with facts/data, which incidentally has a tremendously positive impact on culture. Once established, a fact/data-driven culture can persist for a long time, which is a key ingredient for sustaining competitive advantage. Thanks for the comment. Ron

RCollett
User Rank
Rookie
re: R&D predictability: The path to profitability
RCollett   1/26/2011 2:37:13 AM
NO RATINGS
@Markgrizz, It is definitely obvious -- but remarkably, a great many semiconductor organizations don't understand it. As for an advertisement, you are again correct -- it is an advertisement to think differently about schedule predictability. Rgds, Ron

markgrizz
User Rank
Rookie
re: R&D predictability: The path to profitability
markgrizz   1/25/2011 5:18:02 PM
NO RATINGS
You've stated the obvious, this reads like an advertisement.

Dan Patterson
User Rank
Rookie
re: R&D predictability: The path to profitability
Dan Patterson   1/25/2011 2:46:09 PM
NO RATINGS
Great article. CPM schedules are inherently challenging as the forecasting tool of choice for development type projects. Due to the high degree of uncertainty and iterative work/re-work, traditional CPM Gantt chart type forecasting rarely gives an accurate picture - hence the frequent perception that the project finished late - i would suggest that instead, we simply didn't plan accurately enough. Worse, given projects teams are aware of this shortcoming, the original 'plan on the wall' simply becomes a static picture that doesn't reflect the latest updates, changes and impacts due to risk. An alternate approach is to create a risk-adjusted schedule using a combination of a CPM schedule (e.g. MS Project) combined with a project's risk register and model the impact of the latter on the former using Monte Carlo analysis. Not only does this approach give more realistic forecasts, it is also a means of getting team buy-in into the agreed upon plan. I agree with the author that these projects are indeed predictable; we simply need to do a better job of including the non-deterministic work/outcomes in the original plan/schedule. More thoughts on this at http://goo.gl/KQTuz



EE Life
Frankenstein's Fix, Teardowns, Sideshows, Design Contests, Reader Content & More
Max Maxfield

What's the Best Traveling Toolkit?
Max Maxfield
13 comments
A few years ago at a family Christmas party, I won a pocket knife as part of a "Dirty Santa" game. This little scamp was a Buck 730 X-Tract. In addition to an incredibly strong and sharp ...

Rishabh N. Mahajani, High School Senior and Future Engineer

Future Engineers: Don’t 'Trip Up' on Your College Road Trip
Rishabh N. Mahajani, High School Senior and Future Engineer
9 comments
A future engineer shares his impressions of a recent tour of top schools and offers advice on making the most of the time-honored tradition of the college road trip.

Larry Desjardin

Engineers Should Study Finance: 5 Reasons Why
Larry Desjardin
41 comments
I'm a big proponent of engineers learning financial basics. Why? Because engineers are making decisions all the time, in multiple ways. Having a good financial understanding guides these ...

Karen Field

July Cartoon Caption Contest: Let's Talk Some Trash
Karen Field
159 comments
Steve Jobs allegedly got his start by dumpster diving with the Computer Club at Homestead High in the early 1970s.

Top Comments of the Week
Flash Poll
Like Us on Facebook
EE Times on Twitter
EE Times Twitter Feed

Datasheets.com Parts Search

185 million searchable parts
(please enter a part number or hit search to begin)