krisi   3/20/2012 7:50:17 PM
NO RATINGS
Very true Jim...and this situation is not going to change with silicon getting more complex...only people with deep pockets will be able to afford ASICs...Kris

Jim Finch
User Rank
Rookie
re: Debunking the myth of the $100M ASIC
Jim Finch   3/20/2012 6:21:51 PM
NO RATINGS
The primary reason startup companies spent so much money is because their Generation 1 device is almost never commercially viable. It typically works just fine, even hits key performance specs, but the price performance advantage offered is not sufficient to convince potential customers to move away from their current suppliers. This forces additional time and money to develop Gen 2 and usually Gen 3 devices before the entity can generate significant revenue at acceptable margins. This process adds 3-5 years and $30-50M of wasted capital from a VC perspective. I believe this is the greatest spending culprit for most startup companies. Jim

krisi
User Rank
CEO
re: Debunking the myth of the $100M ASIC
krisi   3/20/2012 12:25:03 PM
NO RATINGS
Keep praying @WaywardGeek...silicon industry has become very mature and real innovation is rare...it is quickly becoming another stable industry like car making for example...we have enjoyed the fun ride while it lasted for 50 years!...Kris

WaywardGeek
User Rank
Rookie
re: Debunking the myth of the $100M ASIC
WaywardGeek   3/20/2012 8:08:36 AM
NO RATINGS
Kudos, Andreas, on a very cool engineering feat. There are niche markets where MPW runs can be a viable production solution, like military, rad-hard, and space. Not every company has to be the next Intel to be successful. However, the reality is that Moore's Law is failing, bit by bit. Fewer and fewer designs make it into the latest fab processes, and the companies that do production there are huge corporations. Rarely do we see the innovative startups that drove Silicon Valley's success, at least in the IC space. I am personally focusing on the mixed signal space, where competitive analog is still reasonably affordable. Even so, at Triad Semi, we focus on reducing up-front NRE, providing quick turn, and lowering risk, as these are issues strangling the industry. So, both you and I have moved into niches where we can innovate at small companies without insane levels of venture funding. That's where Moore's Law is failing us the most. We may still be on track for 28nm and even the next node, but the tech explosion cannot be sustained without the Darwinian competition between new ventures. What are the latest super cool new ideas being produced in 28nm? Well, yours of course, but in volume we're seeing Apple add 4 ARM cores to their iPads. I guess the iPad 4 big innovation will be 8 cores? Then 16? And Intel... 8 cores in my next laptop, with a bigger on-chip GPU? Is this really innovation? Yes, transistors are getting cheaper, but they're also getting dumber, because we just can't afford to enable all the innovators to go be creative in 28nm. I pray for a breakthrough like low cost direct-write e-beam, or something that will enable advanced silicon within reach of a traditional startup.

krisi
User Rank
CEO
re: Debunking the myth of the $100M ASIC
krisi   10/10/2011 4:32:58 PM
NO RATINGS
To@moloned If silicon die is about 1cm2 which is fairly typical you would hundreds of part in 0.35um 6 inch wafer...in 65nm the wafer size would be much larger, 8 or 12 inches so you will get way more than few hundreds... I will leave to Andreas to explain your scaling question...Kris

moloned
User Rank
Rookie
re: Debunking the myth of the $100M ASIC
moloned   10/10/2011 4:27:17 PM
NO RATINGS
I can see how you can get to a few 100s of MPW parts in 65nm, but I can't see how this gets you to several hundred $ each for your chips. Care to explain? In the case your customers are paying this kind of price the second question would be how you plan to scale from a niche product to the mass-market?

Wilton.Helm
User Rank
Rookie
re: Debunking the myth of the $100M ASIC
Wilton.Helm   10/7/2011 6:57:53 PM
NO RATINGS
No question FPGAs have had a huge impact, and by implication what's left for ASIC/SoC is going to be the higher end more costly designs which is a factor skewing the numbers. But FPGAs are so cost effective and even power effecient that just about all but cutting edge, products or consumer products made in very large volumes simply cannot justify custom silicon compared to an FPGA solution. For applications like the segment I'm in, they are absolute salvation. I've discussed with others before the trend towards ASIC and high integration and how small companies and niche markets that never sell things in million piece quantities can survive. The answer is simple. FPGA. The tools can be very affordable and the chips offer a huge amount of capability for very reasonable costs. There are even some out there with analog stuff in them, not to mention some pretty credible both hard and soft core CPU implementations.

krisi
User Rank
CEO
re: Debunking the myth of the $100M ASIC
krisi   10/4/2011 10:53:48 PM
NO RATINGS
The trend of replacing ASICs with FPGA started several years back and will continue with accelerated force. I remember standing at one of the large telecom trade shows showing with pride our ASIC with a Xilinx guy standing behind me and smiling. My demo board had one ASIC surrounded by 8 FPGAs! Kris

Robotics Developer
User Rank
Rookie
re: Debunking the myth of the $100M ASIC
Robotics Developer   10/4/2011 9:11:05 PM
NO RATINGS
Having worked in the ASIC industry for 18+ years I have seen the costs skyrocket from 30K to 1.5million. The real cost was not the NRE but the engineering cost to develop, test/simulate, PCB development and system level efforts. These get really expensive as the chip complexity goes up. That said, if you are doing plain vanilla design with low volumes most work shifted from ASICs to FPGAs. FPGAs were taking over the lower end designs both due to time to market and cost. The numbers of ASIC designers started to fade as fewer and fewer designs were attempted and companies shifted to FPGAs. Using an FPGA for the basic designs makes a lot of sense. The ease of reprogramming and quick turn times offsets the increased chip cost (per part) by allowing faster time to market. The last few chips I worked on were between 1.25 to 2.5 million for NRE alone and took over a year with 8 to 12 engineers. These were the only chips that made sense to engineer due to volume and performance drivers.

jeffw_00
User Rank
Rookie
re: Debunking the myth of the $100M ASIC
jeffw_00   10/4/2011 3:13:33 PM
NO RATINGS
Well said Andreas. A small number of skilled, experienced people can wear many hats, strategically pick only the tools they really need, and get better, more cost-effective results than younger, cheaper, "armies".

Page 1 / 2   >   >>


Most Recent Comments
HitheshM500
 
NIRANKUSH456
 
NIRANKUSH456
 
David Ashton
 
Rich Krajewski
 
sranje
 
MeasurementBlues
 
MeasurementBlues
 
Sanjib.A
Flash Poll
EE Life
Frankenstein's Fix, Teardowns, Sideshows, Design Contests, Reader Content & More
Rishabh N. Mahajani, High School Senior and Future Engineer

Future Engineers: Don’t 'Trip Up' on Your College Road Trip
Rishabh N. Mahajani, High School Senior and Future Engineer
3 comments
A future engineer shares his impressions of a recent tour of top schools and offers advice on making the most of the time-honored tradition of the college road trip.

Max Maxfield

Juggling a Cornucopia of Projects
Max Maxfield
7 comments
I feel like I'm juggling a lot of hobby projects at the moment. The problem is that I can't juggle. Actually, that's not strictly true -- I can juggle ten fine china dinner plates, but ...

Larry Desjardin

Engineers Should Study Finance: 5 Reasons Why
Larry Desjardin
37 comments
I'm a big proponent of engineers learning financial basics. Why? Because engineers are making decisions all the time, in multiple ways. Having a good financial understanding guides these ...

Karen Field

July Cartoon Caption Contest: Let's Talk Some Trash
Karen Field
140 comments
Steve Jobs allegedly got his start by dumpster diving with the Computer Club at Homestead High in the early 1970s.

Top Comments of the Week
Like Us on Facebook
EE Times on Twitter
EE Times Twitter Feed

Datasheets.com Parts Search

185 million searchable parts
(please enter a part number or hit search to begin)